When faced with the challenge of completing high-pressure, time-sensitive, and quality-imperative work, we exceed demands and satisfy our customers time and time again. MSI has constructed miles of both airport runways and taxiways and we continue to help improve airports all around Minnesota.
  • 0341_dmi_1608
  • 0267_DMI_1513
  • DSC01627
  • 200713 (2)

taxiway c-1 reconstruction

  • Owner: Metropolitan Airports Commission
  • Engineer: TKDA
  • Installed a new taxiway at terminal 2 to allow for increased airline traffic
  • Maintained safety, quality and security when working alongside live runways and taxiways

taxiway s reconstruction

  • Owner: Metropolitan Airports Commission
  • Engineer: TKDA
  • Reconstructed Taxiway S at MSP International Airport
  • Removed and replaced 3/4 mile of concrete pavement, adding graded drainage ditches

holman field: st. paul airport

  • Owner: Metropolitan Airports Commission
  • Engineer: SEH, Inc
  • Reconstructed runways and built additional taxiways 

taxiway c extension

  • Owner: Metropolitan Airports Commission
  • Engineer: TKDA
  • Reconstructed and expanded Taxiway C at MSP International Airport

.

msp runway 12r-30l

  • Owner: Metropolitan Airports Commission
  • Customer: PCI Roads
  • Rebuilt one of the major runways at the MSP International 
  • Tight schedule constraints demanded a 24 hours per day and six days per week working week
  • Runway was completed for use on schedule

taxiway c-d phase 2 & 3

  • Owner: Metropolitan Airports Commission
  • Engineer: TKDA
  • Reconstructed and expanded Taxiway C-D Phase 2 & 3  at MSP International Airport

terminal 1 cargo and stores building

  • Owner: Metropolitan Airports Commission
  • Construction Manager: Knuston
  • Site grading, excavation, and fine slab grading for new Cargo and Stores Building at Terminal 1 of MSP Airport